In 30 Seconds
- Residents and social workers allege poor planning, weak drainage and uncleared encroachments, while the Mela administration defends the upgrade and promises quality checks.
- Social activists in Haridwar have criticised a Rs 21-crore road and footpath project funded from the Kumbh Mela budget.
- The project builds footpaths on both sides of major roads, including in Kankhal, Shankar Ashram, Bhagat Singh Chowk and Hill Bypass Road.
Social activists in Haridwar have criticised a Rs 21-crore road and footpath project funded from the Kumbh Mela budget. They allege that poor planning has narrowed roads and worsened traffic congestion in parts of the city.
The project builds footpaths on both sides of major roads, including in Kankhal, Shankar Ashram, Bhagat Singh Chowk and Hill Bypass Road. Activists say the footpaths were laid without first removing existing encroachments, and that electricity poles and trees were left standing in the way. They also say the work has done little to improve drainage.
Social activist J P Badoni said the new footpaths have cut the usable width of key roads, leaving little room for parking and creating bottlenecks. He described an "acute lack of planning" in the footpath and road-widening work. Badoni also warned that inadequate drainage along Hill Bypass Road could cause severe waterlogging in the monsoon.
Residents have questioned construction quality and asked for an inquiry into how the money was used. Local resident R M Dobhal said quality was being compromised at several sites even though a third-party agency had been appointed to monitor the project. He urged the Mela administration to take the matter seriously and act sternly against responsible officials.
The Kumbh Mela administration defended the work. Additional mela officer Dayanand Saraswati said footpaths are essential for the city ahead of the festival, given the large crowds expected. He said authorities are acting against encroachments and inspecting the work regularly, and that there would be no compromise on quality.
The dispute matters because the project is meant to prepare Haridwar for the Kumbh crowds. Whether the narrowed carriageways and drainage gaps are fixed before the festival will shape how well the city handles the traffic and the rains.